British BulletinBritish Bulletin
  • Home
  • News
  • Politics
  • Business
  • Entertainment
  • Lifestyle
  • Health
  • Sports
  • Tech & Science
  • Travel
  • Spotlight
  • More
    • Press Release
What's On

First ‘daylight’ offside goal scored in Canada

19 April 2026

London synagogue firebombed overnight in latest arson attack on Jewish community

19 April 2026

Hannah Spencer accuses Labour of believing working class people ‘don’t care about dogs’

19 April 2026

Camilla, Barack Obama, Tony Blair and David Attenborough pay tribute to late Queen in new documentary

19 April 2026

Rachel Reeves issued warning as £75billion tax raid pushes Britain to ‘peak taxation’

19 April 2026
Facebook X (Twitter) Instagram
Web Stories
Facebook X (Twitter) Instagram
British Bulletin
Subscribe
  • Home
  • News
  • Politics
  • Business
  • Entertainment
  • Lifestyle
  • Health
  • Sports
  • Tech & Science
  • Travel
  • Spotlight
  • More
    • Press Release
British BulletinBritish Bulletin
Home » Ed Miliband warns delays to Net Zero plans are ‘not acceptable’ as wind, solar and battery projects falter
Business

Ed Miliband warns delays to Net Zero plans are ‘not acceptable’ as wind, solar and battery projects falter

By britishbulletin.com17 April 20263 Mins Read
Ed Miliband warns delays to Net Zero plans are ‘not acceptable’ as wind, solar and battery projects falter
Share
Facebook Twitter LinkedIn Pinterest Email

Ed Miliband has issued a stern rebuke to Labour officials, declaring that setbacks to Britain’s Net Zero ambitions will not be tolerated.

The Energy Secretary’s intervention comes as renewable energy schemes face mounting difficulties securing connections to the national grid.


Michael Shanks, serving as Mr Miliband’s principal deputy at the department, has directed criticism at the National Energy System Operator over growing delays linked to inaccurate data and planning complications.

In correspondence addressed to civil servants, Mr Shanks and Ofgem stated: “We have been clear that further slippage is not acceptable and have set expectations for a firm, coordinated response.”

The energy minister has demanded that Neso produce regular progress updates, enabling industry stakeholders to monitor improvements to the system.

Tensions have escalated following Neso’s decision in January to impose a temporary moratorium on fresh grid connection applications, citing an overwhelming backlog of requests.

Substantial additions of wind, solar and battery capacity remain essential if Britain is to achieve Mr Miliband’s objective of generating 95 per cent clean electricity by 2030.

The Government-controlled body took over responsibility for connections when it was separated from National Grid two years ago.

‘Further slippage is not acceptable’ as Ed Miliband issues warning amid grid delays

|

GETTY

Meanwhile, the conflict in Iran has driven up oil and gas prices, pushing petrol costs and household energy bills higher.

Mr Miliband has argued that the Middle Eastern turmoil strengthens the case for accelerating the transition away from fossil fuels.

Claire Coutinho, the shadow energy secretary, cautioned that the rush to connect large volumes of renewable generation would impose significant costs on households.

“If we keep dashing towards renewables before the grid is ready, then we will just keep paying more to switch off wind and solar that can’t get to the right place with an £8billion a year price tag because of Ed’s botched plans.”

Claire Coutinho has urged the Labour Government to ‘change course’ on their approach to Net Zero

| GB NEWS

Ms Coutinho added that the grid infrastructure required for renewables would be “two to three times more than other systems” and would ultimately “land on people’s bills.”

Ministers introduced reforms last year designed to prioritise projects nearing completion within the grid connection queue.

Mr Miliband’s clean power action plan, released in December 2024, described these changes as “critical” to Labour’s 2030 mission, warning that essential projects would otherwise face delays.

According to Mr Shanks, the restructuring has removed 221 gigawatts of stalled or redundant schemes from the waiting list.

Nevertheless, battery storage projects continue to create bottlenecks, with planned capacity exceeding actual requirements.

The difficulties are not new, with Octopus chief executive Greg Jackson revealing in 2024 that a County Durham solar farm faced a 13-year wait for connection, prompting the company to consider overseas investment instead.

Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

Keep Reading

Rachel Reeves issued warning as £75billion tax raid pushes Britain to ‘peak taxation’

‘Indie kid’ turned Audoo CEO shares how he disrupted the music industry

Families on benefits rush to little-known DWP scheme to cover mortgage costs

State pension warning as 450,000 Britons miss out on £575 triple lock boost

Households to be PAID to use more electricity under new energy scheme

Pension savings to be hit by ‘double tax’ under Labour overhaul – what you need to know

Energy bills set to jump £196 in July as Strait of Hormuz turmoil keeps costs high

Your Ring doorbell just unlocked a clever upgrade

Four travel firms collapse leaving holidaymakers out of pocket: ‘Uncertain prospects for refunds’

Editors Picks

London synagogue firebombed overnight in latest arson attack on Jewish community

19 April 2026

Hannah Spencer accuses Labour of believing working class people ‘don’t care about dogs’

19 April 2026

Camilla, Barack Obama, Tony Blair and David Attenborough pay tribute to late Queen in new documentary

19 April 2026

Rachel Reeves issued warning as £75billion tax raid pushes Britain to ‘peak taxation’

19 April 2026

Subscribe to News

Get the latest Brittan News and Updates directly to your inbox.

Latest News

Driving licence changes launching this year will see digital ID rolled out for millions of Britons

19 April 2026

Keir Starmer would have blocked Peter Mandelson over vetting , says David Lammy | UK News

19 April 2026

Women’s World Cup qualifying: Lessons to be learned as Wales chase top spot

19 April 2026
Facebook X (Twitter) Pinterest TikTok Instagram
© 2026 British Bulletin. All Rights Reserved.
  • Privacy Policy
  • Terms
  • Advertise
  • Contact

Type above and press Enter to search. Press Esc to cancel.